|  |  |   The 
        Big Dig, Boston - 
        a project briefby Sean O' Neill
 Director of Communications
 Massachusetts Turnpike Authority
 
 Financial 
        Planning and Funding Strategies
 
        Annual Finance 
          Plan - CA/T was the first Federal Transportation Project in the 
          nation to submit annual finance plans that identified the sources and 
          uses of Federal and third party funds. Subsequently the Federal Highway 
          Administration instituted a national policy that all projects greater 
          than $1B submit annual Finance Plans using the Project's finance plan 
          as their roadmap.
 
Grant Anticipation 
          Notes (GANs) - In order to expedite the Project schedule and leverage 
          Federal funds, the Commonwealth was able to issue bonds that funded 
          the Project using out year Federal funds as the source for retiring 
          the bonds. This concept had not been previously utilized on any large 
          scale nationally but the Commonwealth of Massachusetts was able acquire 
          $1.5B of GANS, or Grant Anticipation Notes, with this innovative program. 
          Programs of this type were subsequently used by several other states. 
          
 
 Advance Construction 
          with Partial Obligation Authority Conversions - The traditional 
          federal obligation process required a State to begin a Project once 
          the State had accrued sufficient obligation authority to fully fund 
          a particular contact or project. Massachusetts was able to spearhead 
          this AC technique where Federal Highway would commit to authorizing 
          a contract to proceed (through Advance Construction or AC) and as obligation 
          authority was distributed each year the State would dedicate that authority 
          to ongoing contracts that had been previously authorized. The Commonwealth 
          shaved at least ten years off of the Project schedule by introducing 
          this scheme in the early 90's. Today it is a commonplace practice for 
          all State's transportation programs. 
 
 Recognition 
          of the Importance of the Statewide Program - The Commonwealth of 
          Massachusetts realized that funding the CA/T Project cannot impact the 
          transportation priorities for the balance of the State. Therefore in 
          the early years of the Project, the Commonwealth established policies 
          for the use of Federal funds that would collectively keep the Project 
          moving expeditiously but provide a level of satisfactory funding for 
          other capital transportation projects within the State. 
 
 Transportation 
          Infrastructure Fund - In the late 1990's the Commonwealth established 
          a dedicated revenue stream for transportation funding that minimized 
          public concerns over the ability of the Commonwealth to provide their 
          share of the Project funding needs. The Transportation Infrastructure 
          Fund or TIF was created whereby revenue from drivers' licenses and other 
          auto related fees would be earmarked solely for transportation purposes.
 
 Third Party 
          Construction - Within the City of Boston there are several agencies 
          advancing their particular construction programs. The CA/T Project envelope 
          at times encroached on the footprint of these other projects. In order 
          to minimize disruption to the public, minimize constructability interfaces, 
          and thus reduce overall cost, it was an early Project policy that the 
          work of the two agencies be combined in common areas alleviating the 
          need to disrupt the public multiple times.   Cost Control and Reporting
 
         Safety Program 
          - The Project has continually adopted the concept of 'zero accidents' 
          on the Project. Safety awareness has been paramount in daily meetings, 
          regular site walk downs, and the overall Project culture. Although there 
          have been accidents on the Project, the Project is extremely proud that 
          its performance has been continually significantly below the national 
          averages that has resulted in high morale within the labor force and 
          significant insurance savings to the Commonwealth 
 
 Share Program 
          - As further encouragement for the contracting community to accent the 
          importance of safety and the 'zero accident' Project philosophy, the 
          SHARE Program was conceived whereby specific contractors with outstanding 
          quarterly safety statistics would receive a cash reward based on their 
          achievements. In many cases this cash reward would be shared directly 
          with their workers.
 
 Owner Controlled 
          Insurance Program - CA/T implemented an owner controlled insurance 
          program as opposed to contractor/consultant procured insurance which 
          eliminates overlapping coverages, allows the MTA to realize economies 
          of scale and promotes the expeditious processing and settlement of claims. 
          It has been estimated that this program saved hundreds of millions of 
          dollars.
 
 Integrated 
          Financial / Cost Database - Oracle database software is utilized 
          to capture projectwide cost trends from all responsible departments 
          which are reported to senior management via the Monthly Cost Trending 
          Program. Computer terminals are deployed throughout the construction 
          field offices and the control project office for project staff to enter 
          real-time cost information.
 
 Cost Containment 
          Committee 
          - This is a formal committee consisting of MTA, FHWA and B/PB staff, 
          which meets regularly to review various cost and schedule suggestions. 
          Examples include various aspects of the design like the specific tunnel 
          finishes, building treatments, roadway materials and construction methods.
 
 Employee Suggestion 
          Program - 
          This is a program to reward employees for suggesting ways to reduce 
          project costs by providing cash bonuses. The cash bonuses are paid on 
          a non-reimbursable basis by the Management Consultant, which demonstrates 
          the Management Consultant's commitment to Cost Containment. It furthers 
          a Cost Containment mind-set for all employees.
 
 Design to 
          Cost Program - This program establishes a contractual Baseline Construction 
          Budget with the Final Design firm. This baseline budget is adjusted 
          throughout the final design phase only for changes to scope. If progress 
          estimates are higher than the baseline budget, the Final Design firm 
          is required to redesign without reimbursement.
 
 Monthly Cost 
          Trend Program - Cost trends across the entire project are captured 
          during each month and reported to senior management for information 
          and decision-making. Uses of project contingency budgets are evaluated 
          and follow-up actions to contain costs are identified.
 
 Early ID Program 
          - This 
          program highlights issues, which potentially could increase project 
          cost. Issues are gathered from all project departments and reviewed 
          weekly by senior project management to mitigate impacts where possible.
 
 Value Engineering 
          Program 
          - During the Preliminary Design Phase, a group of experts from the other 
          B/PB offices were brought in for a one to two week period to review 
          and comment on the in progress preliminary designs.
 
 VECP Program 
          - The Value Engineering Contractor Proposal program awards 50% of total 
          savings realized from a contractor proposed idea to the construction 
          contractor.
 
 Material Disposal 
          Program - 
          Through a Project initiative, an agreement with the city of Quincy was 
          negotiated which saved the Project some $60 million compared to the 
          original disposal concept and further benefited Quincy and Milton by 
          closing landfills at no cost plus converting these city areas to revenue 
          producing properties.
 
 Industry Peer 
          Reviews 
          - The MTA engaged the National Academy of Engineers to perform an independent 
          assessment of the project management and contract administration practices 
          employed on the CA/T project. 
 
Lessons Learned 
          Program 
          - Engineering and Design have always been an evolutionary process. Due 
          to the length of the CA/T Project, capturing lessons learned through 
          a formal program from early construction contracts and corporate experience 
          on other projects could greatly benefit later contracts.
 
 PCA Initiative 
          Program - A significant portion of cost changes during construction 
          result from differing site conditions, with the majority of the cost 
          being the residual schedule impact costs to the contract as well as 
          interfacing contracts. Prior to this program, all such actual site conditions 
          had to be negotiated. To reduce cost, the Project created bid items 
          to obtain competitive pricing for removal of unspecified obstructions 
          and other actual underground conditions.
 
 Constructability 
          Reviews - Throughout all phases of design, the Project utilizes 
          on-project and off-project construction experts to review final design 
          submittals to ensure that the designs are constructible and thereby 
          avoid claims and delays.
 
 Pre Advertisement 
          Open Issue Reviews 
          - Prior to advertising a construction package, unresolved design issues 
          are reviewed by senior design and construction managers (including MTA, 
          FHWA, and B/PB). This group evaluates project exposures and decides 
          whether to proceed from a cost/schedule efficiency viewpoint or wait 
          until the issues are resolved.
 
 Partnering 
          - It has always been the practice of the Project to work harmoniously 
          with the Project's many contractors. To facilitate this concept the 
          Project has utilized a partnering program whereby the owner/management 
          consultant can understand firsthand the concerns and challenges of the 
          contractor and vice versa. This process has greatly improved the traditional 
          adverse owner-contractor relationships and improved communications across 
          the Project.
 
 Issue resolution 
          - As one may expect there are many instances where the view of the contractor 
          is not consistent with the understanding of the owner especially in 
          the area of claims. A formal program to assist resolution of these differences 
          was established by the Project team. This process requires a series 
          of progressive reviews by various levels of management and if that does 
          not resolve the impasse the process involves the use of Dispute Review 
          Boards consisting of off-project experts experienced in claims administration.
 
Claims Avoidance 
          Reviews - 
          In this program, claims analysts from active construction contracts 
          are assigned to review similar contracts still in design, with the intent 
          of minimizing the recurrence of similar claim issues.
 
 Schedule Initiative 
          Program 
          - Time always translates into money. Therefore, CA/T management instituted 
          an aggressive program to identify schedule saving initiatives. Throughout 
          the life of the project, schedule savings ideas have been evaluated 
          based on cost/benefit analyses and technical merit. 
 
 Integrated 
          Project Schedule 
          - Throughout construction, the project has utilized the Primavera CPM 
          product to maintain a project master schedule. This schedule is the 
          product of all individual contractor schedules, identifies all contractor 
          interfaces, and identifies schedule trends against major road opening 
          target dates.
 
 C17AA Incentive 
          Clause - The CA/T construction schedule requires efficient management 
          of multiple/complex contract interfaces. An incentive fee clause was 
          included in the I-93 Tunnel Finishes contract to acknowledge that the 
          Contractor's participation is essential to interface management and 
          to compensate the Contractor for schedule flexibility, ingenuity, and 
          cooperation. 
         Fast Track 
          Approach 
          - At he outset of the Project it was understood that while various parts 
          of the Project were in construction other parts of the Project would 
          still be in the design phase. This industry wide management practice 
          reduced the Project duration by several years, minimizing impacts to 
          the Boston area and reducing the costs attendant with extended schedules.
 
 Project Specific 
          Estimating Database - The Project established an estimating database 
          that was the primary source for pricing the several contract estimates. 
          This database was customized for the CA/T Project scopes of work and 
          work methodologies. It employed crew based estimating methodology whereby 
          very experienced construction superintendents would assign a crew, equipment 
          and other material requirements to a particular scope of work based 
          on the Project's unique working circumstances. The database was continually 
          refined and updated based on the bidding environment on the Project. 
          It did not rely on unit price values from other Projects within the 
          State or other States because those Projects were not of the complexity 
          as the CA/T Project.
 
 Electronic 
          Processing - There are several processes for a mega-project that 
          were traditionally performed in a hard copy environment. The CA/T Project 
          embraced the concept of using electronic means for various processes 
          if appropriate. Various levels of management approved contractor and 
          design consultant invoices electronically. Material requisitions for 
          smaller purchases were processed in electronic fashion. If security 
          could be maintained and the process lent itself to electronic means 
          then the position of the Project was to pursue the electronic availability 
          of such a process.    |  |  |